PM 586 Final Exam/ PM586 Final Exam - University of Phoenix
Latest uploads at PM 586 Final Exam/ PM586 Final Exam - University of Phoenix. Looking for notes at PM 586 Final Exam/ PM586 Final Exam - University of Phoenix? We have lots of notes, study guides and study notes available for your school.
-
2
- 0
-
1
All courses for PM 586 Final Exam/ PM586 Final Exam - University of Phoenix
-
PM 586 Final Exam/ PM586 Final Exam - University of Phoenix 2
Latest notes & summaries PM 586 Final Exam/ PM586 Final Exam - University of Phoenix
PM 586 Final Exam/ PM586 Final Exam (Latest) - University of Phoenix

1. In a strong matrix structure, employees take daily direction from:
Project manager only
Both, but the project manager has greater influence
Both, but the functional manager has greater influence
Functional manager only

2. If the schedule variance is positive and the cost variance is negative, the project’s status is:
Over budget and behind schedule
Under budget and ahead of schedule
Over budget and ahead of schedule
Unde...
- Package deal
- Exam (elaborations)
- • 7 pages's •
-
PM 586 Final Exam/ PM586 Final Exam - University of Phoenix•PM 586 Final Exam/ PM586 Final Exam - University of Phoenix
-
PM 586 Final Exam/ PM586 Final Exam ( 2 versions: 2017, 2018) - University of Phoenix (Already graded A)• By QUIZBANK
Preview 1 out of 7 pages
PM 586 Final Exam/ PM586 Final Exam (Latest) - University of Phoenix

1. In a strong matrix structure, employees take daily direction from:
Project manager only
Both, but the project manager has greater influence
Both, but the functional manager has greater influence
Functional manager only

2. If the schedule variance is positive and the cost variance is negative, the project’s status is:
Over budget and behind schedule
Under budget and ahead of schedule
Over budget and ahead of schedule
Unde...
PM 586 Final Exam/ PM586 Final Exam (Latest) - University of Phoenix

1.	In a strong matrix structure, employees take daily direction from:

Project manager only

Both, but the project manager has greater influence

Functional manager only

Both, but the functional manager has greater influence

2.	The collective term for the formal quality activities and processes is called: 

Quality control

Quality visions

Quality policies

Quality assurance

3.	The EVMS term that represents the value of wo...
- Package deal
- Exam (elaborations)
- • 7 pages's •
-
PM 586 Final Exam/ PM586 Final Exam - University of Phoenix•PM 586 Final Exam/ PM586 Final Exam - University of Phoenix
-
PM 586 Final Exam/ PM586 Final Exam ( 2 versions: 2017, 2018) - University of Phoenix (Already graded A)• By QUIZBANK
Preview 1 out of 7 pages
PM 586 Final Exam/ PM586 Final Exam (Latest) - University of Phoenix

1.	In a strong matrix structure, employees take daily direction from:

Project manager only

Both, but the project manager has greater influence

Functional manager only

Both, but the functional manager has greater influence

2.	The collective term for the formal quality activities and processes is called: 

Quality control

Quality visions

Quality policies

Quality assurance

3.	The EVMS term that represents the value of wo...