In a PERT network, the earliest (activity) start time is the
(Points : 4)
earliest time that an activity can be finished without delaying the entire project.
latest time that an activity can be started without delaying the entire project.
earliest time that an activity can start without violation of precedence requirements.
latest time that an activity can be finished without delaying the entire project.
None of the above
Question 2.2.
PERT and CPM are quantitative analysis tools d...
- Exam (elaborations)
- • 10 pages's •
-
Saint GBA334 module 7 quiz•Saint GBA334 module 7 quiz
Preview 2 out of 10 pages
Question 1.1.
In a PERT network, the earliest (activity) start time is the
(Points : 4)
earliest time that an activity can be finished without delaying the entire project.
latest time that an activity can be started without delaying the entire project.
earliest time that an activity can start without violation of precedence requirements.
latest time that an activity can be finished without delaying the entire project.
None of the above
Question 2.2.
PERT and CPM are quantitative analysis tools d...